Project Overview

Construction of a new central utility plant with an elevator slab and mud slab crawl space.  Elevated slab supported by 53 piers.  Also includes construction of a new transformer and generator pads.

Structure type
Commercial
Location
San Antonio, TX
Completion date
2019-03-30

Elevated pan deck construction over mud slab crawl space.  While constructing the new concrete pavement the loading dock must be left operational so T&D Moarvits used a high early strength concrete so trucks could drive on new concrete within 24 hours of placing concrete.